Fauquier County restricts future data center development with new zoning rules

The Fauquier County Board of Supervisors has adopted new zoning rules for data centers, essentially restricting development to one area of the county.

The zoning text amendment, approved Oct. 8, restricts new data center projects to land zoned for planned commercial industrial development, or PCID, and removes data centers as a permitted use in areas zoned as business park, or BP. Prior to the zoning change, data centers were only allowed in areas zoned PCID or BP.

The measure passed by a 4-1 vote, with Supervisor Daron Culbertson, of the Lee District, casting the sole dissenting vote. Only one speaker came forward during the public hearing, expressing support for the “excellent change.”


Related stories

  • AI data centers are coming for federal land. They are roiling the Nevada governor’s race
  • Close to home or across the state, Marylanders don’t want data centers, poll finds
  • Fairfax County community weighs in on Dominion-NextEra Energy merger as concerns grow over data centers, electric bills

In a presentation to the board, staff noted as a reason for the amendment that applications for business park data centers have been largely unsuccessful. One, Remington Technology Park, has been approved and is under construction, while another eight proposals have been withdrawn.

The presentation stated there are “no appropriate areas for data center development” outside of areas zoned PCID. Staff cited recurring concerns across several projects, including electrical grid strain, proximity to housing, environmental impact and more.

Culbertson is intimately familiar with the lack of success of business park data center proposals, as he was part of the group that withdrew an application for a Remington-area data center last month. In his comments prior to Thursday’s vote, he called himself the “odd man out” and reiterated his belief that data center development could be an economic boon for the county.

“From someone who’s spent their entire adult life working with farms and doing work for John Marshall Soil and Water, I did not want to see conservation or agriculture not be the main focus of our county,” Culbertson said. “But I also realized that there are things that need to be done when it comes to a tax revenue and economic development base.

“I thought there was a way that we could use data centers to accomplish everything that we want to accomplish, but in a responsible way,” he added.

The Vint Hill area is the lone part of Fauquier County currently zoned planned commercial industrial. Assistant Director of Community Development Adam Shellenberger said at a Sept. 17 planning commission meeting it is “probably unlikely” that anybody would rezone to planned commercial industrial, though they could apply.

In addition to removing data centers as a use in the business park district, the text amendment requires any future data center in the PCID district to obtain a special exception. It also adds definitions for data centers and data and computer services and clarifies that office, limited industrial use and warehousing designations are not to include a data center.

Even in the PCID district, the ordinance clarifies “purpose and intent,” asserting that data centers are to be “secondary and compatible” with the “limited commercial, business, recreational and light industrial park uses within the approved development.” It also requires future data centers to use closed-loop or air-cooled systems and to have any power lines be underground.

The changes outlined in the ordinance do not apply to the three projects already approved or in the approval process in the PCID district, including the already operational OVHcloud.

Source